E. University Closure Nov 17-20

Filed under: Construction Notices — Nancy Shore @ 1:40 pm

FYI:

Notice of Temporary TRAFFIC CONTROL PLAN

E.university avenue (Willard St to S. University)

Monday November 17, 2008 TO thursday november 20, 2008

Location and Limits of Affected Area:

E. University Avenue from Willard St. to S. University

Description of Construction:

The O’Neal Construction Inc. will disassemble and remove from E. University Ave, the construction crane that was utilized during the Zaragon development project. This temporary road closure is necessary for the safety of the public.

Temporary Construction Traffic Control Plan:

At 7:00 a.m. Monday November 17, 2008 through Thursday November 20, 2008 the NB traffic on E. University Ave will be directed east on Willard St, north on Church St, and west on S. University. The E. University SB traffic will be directed south on Church St, and south on Tappan St. From Church St. the traffic will be directed southerly to Willard St, west on Willard St. back to E. University. From Tappan St. the traffic will be directed south to Hill St. then east on Hill Street back to E. University.

Pedestrian Traffic

Pedestrian traffic will be maintained throughout the project on the west side of E. University Street. Access to all businesses will be maintained at all times.

Project Contacts:

City of Ann Arbor

Troy Baughman, Project Engineer, (734) 997-1695

David Clemons, Technician Supervisor, (734) 323-7942

John T. Brink, Technician, (734) 323-3893

O’Neal Construction

Darryl S. Bell, Project Superintendant, (734) 320-2440

Connelly Crane Rental Corp.

Tim Roy, Project Representative, (313) 999-3095

• • •