Notice of Temporary Traffic Control Plan
South State Street from Mckinley ave. to granger ave.
7:00 AM Saturday November 22, through 6:00 AM Monday November 24, 2008
and
7:00 AM Saturday December 6, 2008 through 6:00 AM Monday December 8, 2008
Location and Limits of Affected Area:
S. State Street, from Stimson St to Packard St.
Description of Construction:
The UM contractor for the Indoor Football Practice Facility will install a new storm sewer lead from the building site to the existing storm sewer main on S. State St, and will restore the road pavement road after the completion of the underground utilities.
Temporary Construction Traffic Control Plan:
The local and southbound traffic will be maintained at all times. The through northbound traffic will be directed east on Stimson, north on S. Industrial, east on Stadium Blvd and north on Packard St and back to State Street.
Pedestrian Traffic
Pedestrian traffic will be maintained throughout the project on the East side of S.State Street. Access to all residences will be maintained at all times.
Project Contacts:
City of Ann Arbor
Troy Baughman, Project Engineer, (734) 997-1695
David Clemons, Technician Supervisor, (734) 323-7942
Chris Rachwal, Technician, (734) 323-7144